- The two pads these sit on. The first one needs to come in and be brought over to the other pad. We will come back 2 weeks later to install the other chiller.
-
- This tank actually needs to be brought in first and hung above the large chilller and then lowered back down on top of it because it is too tall to fit through the door.
-
- We use a fork truck to set the tank on top of the first chilller. The next time we go back there will be no room for the fork truck so we will use a beam clamp and chainfall from the ceiling.